This tutorial explains the construction stage analysis of a Prestressed Concrete Box Girder Bridge using the Free Cantilever Method (FCM) in Midas Civil. It details modeling, material definition, prestressing, and time-dependent analysis, focusing on general functions rather than the FCM Wizard.
主要内容
Construction Sequence and Stage Analysis
Outlines the construction sequence for a 3-span FCM bridge built using four form travelers, including substructure construction, segment erection, key segment construction, and final finishing.
Modeling and Material Definition
Covers defining materials, section properties, and the creation of prestressed concrete box girder and pier models. Includes the definition of time-dependent material properties for creep, shrinkage, and prestress loss analysis.
Boundary Conditions and Load Groups
Describes how to assign boundary conditions, including fixity at piers and longitudinal rollers at the girder ends, and defines load groups for self-weight, prestress, form traveler loads, wet concrete loads, and time-dependent loads.
Construction Stage Definition
Explains how to define and arrange construction stages, including activation/deactivation of structure, load, and boundary groups, as well as handling time-dependent effects like creep and shrinkage.
Prestressing and Tendon Profiling
Guides the user through tendon property definition, tendon profile creation, and the application of prestress forces at each construction stage, including post-tensioning sequences and grouting.
Load Applications and Analysis
Covers inputting various loads, such as self-weight, form traveler loads, wet concrete loads, and time loads for aging effects. Describes performing structural analysis and evaluating the results.
Result Interpretation
Explains how to interpret construction stage analysis results, including deformations, stress distributions, tendon forces, and time-dependent effects, with guidance on validating the model and ensuring code compliance.
This tutorial provides a comprehensive workflow for conducting construction stage analysis of FCM bridges using Midas Civil, offering detailed guidance on modeling, prestressing, load application, and time-dependent analysis to ensure accurate simulation and code compliance.