This third instalment of the high-rise design series condenses the column shortening problem and its treatment into a single presentation. It explains the elastic and inelastic components of vertical shortening, the serviceability and structural problems that differential shortening causes, the layout measures and level corrections that mitigate it, and the construction stage analysis workflow in midas Gen that quantifies it. It draws on the companion construction stage analysis series for the detailed procedure.
핵심 내용
Elastic and Inelastic Shortening
Shortening of a vertical member combines elastic shortening under dead and live load with inelastic, permanent shortening from drying shrinkage and creep, the two contributions being of similar magnitude in a very tall concrete building. Concrete columns shorten several times more per story than core walls, so the accumulated difference at roof level of a tall tower is large. Over a typical column-to-wall span that relative movement implies a very steep inclination of the connecting horizontal member.
Consequences of Differential Shortening
Relative displacement develops between the core wall and the columns and between outer and inner columns, and because the deformations accumulate up the height the effect grows with the number of stories. Structurally it distorts slabs and beams and redistributes gravity load, and non-structurally it breaks finishes, imposes additional load on a glazed facade, and disturbs elevator rails, door frames, partitions and piping. The problems are therefore both strength and serviceability matters.
Root Cause in the Axial Force Ratio
The axial force ratio, gravity load divided by the compressive capacity of the section, is much lower in a core wall than in a column because the wall is sized largely by lateral load. Since that ratio drives the elastic and creep strain, the two member types shorten at different rates by construction. Because the ratio also governs member sizing, the differential is intrinsic to the usual arrangement rather than an avoidable defect.
Design-Stage Mitigation
Two layout measures are recommended: choosing column sizes so that the vertical members have similar axial force ratios, and increasing the distance between columns and walls and between adjacent columns so that a given relative displacement induces less additional stress in the connecting members. The original plan and the revised plan are shown side by side. Where additional forces remain, flexural and shear reinforcement is added to the affected slabs and beams.
Level Correction During Construction
Inelastic deformation is compensated by casting each column and wall higher than nominal by its own correction value, with packing at the formwork, so that the slab or beam reaches its planned level years later. The correction differs between columns and walls because their shortening differs, and the presentation illustrates the planned level alongside the corrected wall and column levels.
Three-Analysis Workflow
A preliminary construction stage analysis using design material properties, section properties, loads and the planned construction process feeds the additional stresses from unequal shortening back into the structural design. A second analysis substitutes material properties measured by experiment, namely compressive strength, modulus of elasticity, creep and drying shrinkage, and the actual construction process. A third analysis incorporates strain gauge measurements taken on site, predicts the shortening of floors not yet built and produces the correction values.
Construction Stage Analysis in midas Gen
The program workflow defines materials, then time-dependent functions for creep and shrinkage and for compressive strength which are linked to the member materials, groups members, boundaries and loads for staged activation, defines the stages from the construction schedule, sets the analysis control data and runs the analysis. Results split into member forces, which are combined with wind, seismic and the separate creep and shrinkage load cases into design combinations for member design, and shortening values at target nodes, which are reported per component and exported to a spreadsheet for determination of the correction values.
Differential shortening between columns and core walls arises from their different axial force ratios and is roughly half attributable to creep and shrinkage, producing both additional member forces and widespread damage to finishes and services. It is managed by equalising axial force ratios and increasing member spacing at the design stage, by adding reinforcement where forces remain, and by construction stage analysis in midas Gen that is progressively refined with material test data and site strain measurements to set the level corrections.