This second part of the midas Gen construction stage analysis series explains why column shortening makes staged analysis essential in high-rise design. It breaks vertical member shortening into elastic and inelastic components, describes the structural and serviceability problems caused by differential shortening between walls and columns, and shows how much error conventional analysis introduces. It closes by distinguishing the shortening that occurs before and after each slab is cast, which determines what the engineer can compensate.
Key Topics
Elastic and Inelastic Components of Shortening
Shortening of a vertical member is the sum of elastic shortening under dead and live load and inelastic, essentially permanent, shortening from drying shrinkage and creep. For a very tall concrete building the two contributions are of comparable magnitude, with the inelastic part typically slightly the larger. Because the shortening accumulates floor by floor, the total at roof level is large enough to matter for both the frame and the facade.
Differential Shortening Between Vertical Member Types
Concrete columns shorten several times more per story than core walls, so the difference accumulates over the height of a tall building and can reach a substantial value at roof level. The same effect appears between outer and inner columns, which carry different tributary loads. Over a typical wall-to-column span this relative movement corresponds to a very steep inclination of the connecting horizontal member, which is why the accumulated differential rather than the absolute shortening usually governs.
Root Cause in the Axial Force Ratio
The axial force ratio, gravity load divided by the compressive capacity of the section, is far lower in a core wall than in a typical column, while a column with a large cross section falls in between. Since that ratio drives the elastic and creep strain, walls and columns of the same height shorten by different amounts, and columns of different size differ from each other as well. Because the ratio is also a governing factor in member sizing, computing the resulting shortening accurately with a program is unavoidable.
Serviceability Problems Caused by Shortening
Absolute shortening deforms elevator rails and door frames and can cause failure of vertical finishing materials and the external curtain wall. Relative shortening reverses the slope of plant piping and damages partitions and floor finishes. Movement of the frame can also break glazing or impose additional load on the facade, so the effects reach well beyond the structure itself.
Error in Conventional Analysis
For a typical forty-story reinforced concrete building, drying shrinkage and creep account for roughly half of the total differential shortening between column and core wall. Comparing conventional analysis with staged analysis including elastic, creep and shrinkage effects shows a difference of about a quarter in the predicted differential shortening and a smaller but still significant difference in the beam end moment at the wall. Conventional analysis therefore misstates both the movement to be compensated and the forces to be designed for.
Compensation and Additional Reinforcement
Two families of remedy are described: correcting the construction level of each column and wall by the predicted inelastic deformation, using packing at the formwork so that the slab or beam reaches its planned level years later, and adding flexural or shear reinforcement to slabs and beams to carry the additional forces that differential movement induces. The correction value differs between columns and walls, so the levels are adjusted member by member.
Shortening Before and After Slab Pouring
Total column shortening splits into the part occurring up to the slab pour and the part occurring afterwards. The portion before pouring needs no level correction in a concrete building and produces no additional force or finishing damage, though in a steel building the column must still be fabricated longer to allow for it. The portion after pouring is the one that requires level correction in concrete buildings and that generates additional member forces and damage to finishes, and in a steel building it too must be added to the fabricated length.
In high-rise buildings the accumulated difference in shortening between core walls and columns, roughly half of which comes from creep and shrinkage, causes both additional member forces and widespread serviceability damage. Conventional analysis misestimates this differential and the resulting girder moments by a significant margin, so construction stage analysis is required to size members correctly and to set the level corrections applied during construction.
