[EN_GEN] Construction Stage Analysis for Column Shortening

PDF
·
37ページ
·
6.9MB
·
English
·
2025.03.11 更新
概要

This presentation introduces column shortening in high-rise buildings and shows how midas Gen construction stage analysis is used to predict and compensate for it. It covers the physical sources of shortening, its structural and non-structural consequences, real project applications, the step-by-step modelling procedure, supporting program features, and a closing software demonstration. The material is aimed at engineers who must supply compensation values to the field.

主要内容

01

Sources and Effects of Column Shortening

Shortening of a vertical member arises from elastic stress under gravity load, creep caused by sustained gravity load, drying shrinkage, and temperature variation in exposed columns; for concrete columns the creep and shrinkage contributions are comparable in size to the elastic part, whereas a steel column shortens elastically only. Structurally, differential movement distorts slabs and beams and redistributes gravity load between vertical elements. Non-structurally it deforms pipes, elevator rails and cladding and cracks partitions.

02

Why Sequential Loading Must Be Modelled

Dead load is applied sequentially as the building rises, unlike live, wind and seismic load which act on the completed structure. Comparing girder end moments at wall connections with and without sequential loading shows that the assumption of instantaneous loading of the finished frame misrepresents the actual distribution. Construction stage analysis is therefore needed both to capture this and to provide compensation values for differential shortening.

03

Pre-Slab and Post-Slab Installation Shortening

Shortening is divided into the part that occurs before the slab is installed at a given level and the part that occurs afterwards, which determines what must be compensated. In a reinforced concrete structure the pre-installation part is unimportant because it is absorbed by levelling the forms, so only the post-installation shortening from subsequent loads and from creep and shrinkage matters. In a steel structure the columns are fabricated to exact length with attachments carrying the slabs, so the pre-installation shortening must be known and the compensation covers the sum of both parts.

04

Field Application Procedure

The recommended workflow starts from material and section properties, loads and the construction sequence, runs a pre-analysis for column shortening, and considers the load redistribution caused by differential shortening. Material properties for compressive strength, modulus of elasticity, creep and shrinkage are then updated from laboratory experiments and the sequence is revised to match actual site conditions. Shortening is measured in the field with strain gauges, and a re-analysis predicts the remaining movement of later stages and supplies the compensation amounts.

05

Project Applications

The presentation cites three towers analysed for column shortening: the Burj Khalifa in Dubai, an office and residential tower over seven hundred metres tall with about one hundred sixty floors; SK S-Trenue in Seoul, a thirty-six story composite office building on a mat foundation with a reinforced concrete core combined with steel and composite framing; and the Keangnam Hanoi Landmark Tower in Vietnam, a reinforced concrete hotel, office and residential complex of about three hundred forty-five metres.

06

midas Gen Modelling Procedure and Features

The workflow in the program is to define materials and sections, define time-dependent material properties for creep, shrinkage and compressive strength gain, assign elements, boundaries and loads to groups, enter the construction stage data with stage durations and the activation or deactivation of element, boundary and load groups, then run the analysis and review results stage by stage before extracting column shortening. Time-dependent behaviour accounts for members cast at different maturities, so creep, shrinkage and stiffness all vary with the age of each element. The session ends with a live demonstration of these features.

まとめ

Column shortening in tall buildings is driven by elastic, creep, shrinkage and thermal effects, and the resulting differential movement affects both structural forces and non-structural components. midas Gen construction stage analysis with time-dependent material properties predicts pre-slab and post-slab installation shortening so that compensation can be specified, and the approach has been applied to major towers including the Burj Khalifa.

関連資料

同じカテゴリー・トピックから厳選した資料です。

STRUCTURE · MIDAS NOTE[KR_GEN] 기둥축소량의 해석 및 최적보정 그리고 실무적용
STRUCTURE · SEMINAR[KR_2004.05] 시공단계해석을 이용한 초고층 건축물의 설계 및 시공(정재경)
STRUCTURE · MIDAS NOTE[EN_GEN] Highrise building design in midas Gen
STRUCTURE · MIDAS NOTE[EN_GEN] Construction stage analysis_S02 Why do Construction Stage Analysis in high-rise buildings