[EN_GEN] Construction stage analysis_S04 What should an engineer do for column shortening

PDF
·
9ページ
·
1.3MB
·
English
·
2025.03.11 更新
概要

This fourth part of the midas Gen construction stage analysis series sets out what the structural engineer is expected to do about column shortening, from the planning stage through construction. It presents a three-analysis workflow that moves from a preliminary prediction, through material testing and site measurement, to a corrected prediction used to set compensation values. It also covers layout and joint decisions that reduce differential shortening in the first place.

主要内容

01

Three-Stage Analysis Workflow

A preliminary construction stage analysis uses design material properties, section properties, the acting loads and the planned construction process, and its results feed the additional stresses caused by unequal shortening back into the structural design. A second analysis is run once material experiments have established the real compressive strength, modulus, creep and shrinkage behaviour, and once the actual construction process is known. A third, main analysis then incorporates the site measurements and produces the correction values that are applied during construction.

02

Layout Control at the Design Stage

Differential shortening can be reduced before analysis by choosing column sizes so that vertical members have similar axial force ratios, since it is the difference in that ratio that drives the differential movement. Increasing the distance between a column and the wall, and between adjacent columns, reduces the additional stress transferred through the connecting horizontal members for a given relative displacement. The presentation illustrates how an original column layout can be revised on both counts.

03

Reviewing Additional Stresses and Reinforcement

The design review must check the additional stresses and the resulting reinforcement demand in slabs and beams, and separately in outrigger and belt truss members, which are highly sensitive to relative movement between the core and the perimeter columns. Construction alternatives should also be prepared for the differential displacement at the connection between the high-rise tower and the low-rise podium. These checks turn the predicted movement into concrete detailing decisions.

04

Joint Location and Timing

Joints are reviewed with the aim of minimising the additional stress they must carry. Two decisions are highlighted: where the outrigger joint is placed and when it is closed, and what connection detail is used between the high-rise and low-rise portions and at what time it is made. Delaying closure until much of the differential shortening has occurred is the practical way to relieve these members.

05

Material Experiments

Three sets of concrete tests support the second analysis: compressive strength and modulus of elasticity measured at several ages up to about ninety days, a creep test giving the specific creep strain over roughly three to four months, and a drying shrinkage test giving the ultimate shrinkage strain over the same period. These measured properties replace the code default values in the model, since the code models are calibrated to generic rather than project-specific concrete.

06

Site Measurement and Its Limits

Strain gauges installed in the main vertical members measure actual strain under real field conditions, capturing site temperature and humidity, initial curing conditions, the true load history and the actual mix. The presentation notes the practical difficulties: results are sensitive to the initial curing temperature, the gauges need disciplined management with readings roughly twice a week, and obtaining the total shortening of a column is hard because of the limited number of sensors that is economically feasible. Analysis and measurement are therefore treated as complementary, with the measurement used to correct the analysis.

07

Scaling and Optimal Compensation

The predicted shortening curve from midas Gen is scaled to pass through the measured values, giving a corrected prediction for the floors not yet built. Compensation is then applied by casting each column taller than nominal by the correction value, with filler at the pour line, so that the slab reaches its planned level at completion. Because a separate correction for every floor is impractical, floors are grouped and one correction value is used per group, with the group chosen so that the difference between the predicted and applied correction stays within the allowable value at each story, following published work on optimal compensation of differential column shortening.

まとめ

Handling column shortening is an iterative engineering process rather than a single calculation: predict it, design the layout and joints to limit it, verify the material properties by test, measure the real strains on site, and rescale the prediction to set compensation values. Applying those corrections in floor groups, with the residual per story kept inside an allowable limit, brings the completed slab levels back to the planned geometry.

関連資料

同じカテゴリー・トピックから厳選した資料です。

STRUCTURE · MIDAS NOTE[KR_GEN] 기둥축소량의 해석 및 최적보정 그리고 실무적용
STRUCTURE · MIDAS NOTE[EN_GEN] Highrise building design in midas Gen
STRUCTURE · MIDAS NOTE[EN_GEN] High-rise building design_S03 Column shortening in High-rise design
STRUCTURE · MIDAS NOTE[EN_GEN] Construction stage analysis_S02 Why do Construction Stage Analysis in high-rise buildings